THE $6 million “affordable” homes project in Marine Pde, Hastings, will not be finished until next year. A halt was called on work to complete the 20 homes earlier this year when builders unearthed a disused fuel tank. Since then the land has been extensively tested to gauge the extent of contamination from the tank left over from a former service station. “It’s really sad this has happened,” state manager for Community Housing Ltd Brett Wake said on Monday. “We’re very confident we’ll be able to finish the project, but it won’t be until the next calendar year.” Mr Wake…